Milestone

Submission of DPR to CEA Date: 31.03.11 Data collected by M/s WAPCOS for the preparation of DPR.
Award for construction of roads: Kuanpani to Num, Num to Dam site ‘Faksinda/Dobhan’, Chhainkuty to Diding (Power House Site) Target Date: 28.02.11 Cost estimate prepared .
Construction of Transit camp at Faksindha/Dobhan (Dam site) Date: 31.10.10 Approval from Corporate office is awaited.
SES/ SIA Studies Target Date: 31.10.10
Signing of Project Implementation Agreement with Govt. of Nepal Date: 31.07.10
Taking over the land for the access roads from NEA 31.12.2009 In progress.